|
|
|
|
Kyoto Flexible mechanism in EEC - case SlovakiaJ. Balajka Profing s.r.o. Bratislava
This paper try to discuss above issues, using the experiences gained in Slovakia
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Fuel
|
h/year
|
MWt
|
efficiency
|
TJ/year
|
kgCO2/GJ
|
ktCO2/year
|
CO2kt/year
|
| brown coal |
4000
|
100
|
78%
|
142.5
|
98.4
|
14.0
|
14.0
|
| NG |
4000
|
100
|
88%
|
126.3
|
58.6
|
7.4
|
7.4
|
| wood |
4000
|
100
|
75%
|
148.1
|
0
|
0.0
|
|
It is clear, that for project owner the coal baseline is more convenient and can bring larger financial resources from emission trading. The same interest is of investor, because at the same investment money the large volume of ERU's can be transfer. The position of MoE could be quite different. The environmental legislation that forces the energy producer to fuel switch is presented as accepted political issue to CO2 abatement, and should be included in national baseline for additional measures. There is question which baseline will be accepted by MoE at JI project approval.
The other confusing point of JI project baseline is competition of demand
side and supply side projects. . Let us consider the same heat sources,
that supply the heat in residential area. Due the Demand Side Option (DSO)
- thermal building insulation the average load declines from 100 to 70
MWt. As is seen, it decreases the abatement level for fuel switch measure
of 30%. On the other side also the type of fuel combustion influences
the impact of DSO. In the case of coal as fuel, impact of thermal insulation
will be 4.2kt/year. In the case of gas it will be 2.2 kt/year and at application
of JI based on the wood use the impact of DSO will not bring any effect.
There is question how allocate the ERU's at two simultaneously applied
processes?
|
average load MWt
|
fuel TJ/year
|
CO2 kt.year
|
||||
| Fuel |
baseline
|
DSM
|
baseline
|
DSM
|
baseline
|
DSM
|
| brown coal |
100
|
70
|
142.5
|
99.7
|
14.0
|
9.8
|
| NG |
100
|
70
|
126.3
|
88.4
|
7.4
|
5.2
|
| wood |
100
|
70
|
148.1
|
103.7
|
0.0
|
0.0
|
There are several approaches to calculate abatement cost. One of them represents Marginal Abatement Cost MAC as the cost of last CO2 tonne abatement. The other one, recommended by World Bank to GEF projects, is so called Incremental Cost IC representing by the common formula:
IC = NPV project - NPV baseline / CO2 emission baseline - CO2 emission project
While MAC can be calculated with the use of sophisticated programme (ENPEP, MARKAL) on the national level, the incremental cost is more proper for JI due its project oriented character. As is seen from above formula, the baseline definition will play again very important role. Let us look again on the previous project with biomass implementation. The abatement cost will be very dependent on the baseline.
As was stated above, the baseline will be different at the different fuel and different heat demand. The later is dependent on the fact if simultaneously DSO e.g. thermal building insulation is implemented. The next table gives the results of abatement cost calculation of in table 1 and 2 presented cases, e.g. different fuel and different heat demand at biomass use as JI project. The 100 MWt heat source with 129 USD/kWt investment cost and 15% discount rate were considered.. The fuel cost and its price escalation are in agreement with data proposed in Energy Policy of SR.
Table 3 Abatement cost of JI project
|
DSO - thermal insulation
|
Baseline
fuel |
NPV
|
CO2
|
IC
|
|
'000'USD
|
kt
|
USD/t
|
||
| is not implemented | coal |
2720
|
181.7
|
15.0
|
| gas |
-3313
|
95.9
|
-34.5
|
|
| implemented | coal |
9591
|
127.2
|
75.4
|
| gas |
5367
|
67.2
|
79.9
|
It is seen, that lowest abatement cost is achieved at the case of NG as the baseline fuels. The decrease of heat demand will bring the turn over to the positive and highest value..
In order to ranking the individual measures type on the national level, the cost curves use to be designed,. Some examples of cost curves in the Slovakia case are on the figure 4 and 5, The cost curves were designed for the higher and lower range of abatement cost values, considering uncertainties of technology investment cost and project baselines.

| Comments: | I nd. energy represents the industrial HP and CHP DH centralised district heat supply GT in DH Geothermal energy for centralised DH supply Public CHP Cogeneration plants of regional public utilities, JI project consider replacement of existing coal CHP by CC with cogeneration |
The difference in abatement cost indicates uncertainties, that can arise at project assessment on the national bases. Despite that, the projects based on the biomass use seem to be most proper as JI projects. On the other hand, implementation of CC indicates highest abatement cost, as is seen from above cost curves. We must realise, that abatement cost of CC implementation will not reflect real private cost of this project type. In abatement cost calculation is not included the grid electricity price relation that is most important issue at decision making process. Therefore CC in industrial energy will be implemented outside JI framework and the impact on emission level will be dependent on the grid electricity fuel mix.
The above mentioned uncertainties connected with the technical and economical
background of JI projects create some fundamental question - Is JI
better option for country with economy in transition as other option like
AT?
The next table summarises the main feature and its difference between
JI and AT.
|
ITEM
|
ALLOWANCE TRADING
|
JOINT IMPLEMENTATION
|
| Commodity | Allowances(permits) | Credits(offsets) |
| Compliance | Based on emission inventories | Based on project monitoring |
| Institutions | International market | Ad hoc trades approved by governments |
| Reference | National cap | Project baseline |
| Emission monitoring | National inventories | Project emissions |
| Incentive for seller/host | Revenues to national budget(environmental fund) | Revenues to project |
| Incentive for buyer/investor | Lower abatement costs | Lower abatement cost |
| Implementation of reductions | Policy instruments | Direct technology investment |
| Transaction costs | Low | Possibly high |
| National implementation cost | Possibly high | Low |
| Reduction potential | Large | Limited |
| Time horizon | After 2008 | About 2000 |
| Development | International market construction as a whole | Gradual evolution of market |
Considering the special condition of country in transition, the following issues should be taken in consideration too?
1. The lack of investment resources, needed by the start of project gives
preference to the JI over AT.
2. The financial income can be drowned in the case of AT in national budget.
3. There are not many large JI projects in small size countries. On the
other hand large JI potential is in many small projects characterised
by large transaction cost comparing with the total financial resources
gained from emission trading. From this point of view AT represents some
advantage.
4. Together with transaction cost, each JI project represents the large
bureaucratic bottleneck, specially for small size project one.
5. As is seen from previous analysis, the reliable project baseline can
be designed for supply side projects with the same allocation of financial
resources and emission reduction. On the other hand the simultaneously
implemented demand side projects can decrease the supply side JI project
impact too..
6. The baseline of JI depends on the economical activity, that prediction
is very difficult in labile economical environment of countries in transition.
Considering all pro and contra what should be better JI or AT?. There are two ways that represents to compromise between JI and AT.
1. Establishing the emission cap for decisive CO2 emission sources. It
gives the possibility for domestic and international CO2 trading and simplifies
the process of monitoring and governmental control. The experiences from
USA SO2 trade can be applied here. The problem is in the determination
of this cap - will be used grandfathering approach or cap will be sized
according some special indicators (production output, etc.)?
2. Similarly as in the case of some just establishing Carbon Fund ( WB
and/or others), it is possible to create this fund on the national basis.
The fund can give the loan for the project owner on the beginning of project.
Loan can be pay back by the CO2 credits or repayment. The later will be
applied, if yearly emission decrease will not be proved. Fund can sell
credit to the foreign or domestic customers. Nevertheless governmental
approval will be needed in the case of credit transfer in abroad for individual
year, depending on the CO2 national balance. Some compromise between repayment
and credit transfer can be applied. The problem is to collect money at
the beginning of fund creation in country with economy in transition and
foreign investment will be in any case needed.
The
Regional Environmental Center for Central and Eastern Europe (REC)
Ady Endre út 9-11, 2000 Szentendre, Hungary
Tel: +36 26 504-000; Fax: +36 26 311-294; E-mail: climate@rec.org